← Tarbela Dam

Version 1

Nov 10, 2026. Compare with the current version · Version history

Tarbela Dam is an earth- and rock-filled dam on the Indus River in Pakistan, about 60 km northwest of Islamabad, built in the 1970s to store river water for irrigation and since expanded into a major source of hydroelectric power.

Tarbela Dam and its reservoir on the Indus River in Pakistan.
Tarbela Dam and its reservoir on the Indus River in Pakistan.

Via Wikimedia Commons: Tarbela Dam, KPK, Pakistan by w:USAID, public domain.

Overview

The World Bank's 2012 appraisal of a power project at the dam describes it as the world's largest earth and rock filled structure, 485 feet (148 metres) high and 9,000 feet (2,743 metres) long. An earth- and rock-filled dam, or embankment dam, holds back water with a mass of compacted soil and rock rather than with concrete. A World Bank completion report of 1992 put its scale another way, noting that the volume of its earth fill was three times larger than the Aswan High Dam of Egypt.

The dam plays three roles: it stores water for irrigation, generates electricity and reduces floods. The same 2012 document states that it is operated with priority for irrigation and produces hydropower as a byproduct, storing the Indus's summer flood flows and releasing them in the dry winter months. It supplies water to the whole Indus Basin Irrigation System, which the World Bank calls the largest irrigation system in the world. The dam has five tunnels through which water can be released and two spillways, channels that carry surplus water past the dam; in 2012 the Bank noted that more than 70 percent of the water reaching it each year passed over the spillways rather than through the turbines.

Origins in the Indus Waters Treaty

The dam grew out of the partition of British India in 1947, after which most rivers of the Indus system flowed through India before reaching Pakistan. After close to ten years of negotiation, the two countries signed the Indus Waters Treaty in 1960. In the summary given by the Asian Infrastructure Investment Bank (AIIB), it allocated three Eastern Rivers (Ravi, Sutlej and Beas) to India and the three Western Rivers, the Indus, Jhelum and Chenab, to Pakistan, which was to meet the needs once served by the eastern rivers by building "replacement works".

Tarbela was built as part of that programme, known as the Indus Basin Project. The World Bank's 2012 document states that its purpose was to compensate for the loss of water supplies of the eastern rivers that India would now use exclusively. According to the AIIB, donors including the World Bank provided Pakistan with close to one billion US Dollars toward these works, among them the Tarbela Dam on the Indus and the Mangla Dam on the Jhelum.

Construction and first filling

Tarbela had its own financing arrangement. The World Bank's 1992 report records that a Tarbela Development Fund was established in 1968, with foreign exchange contributions from several industrialised countries and a Bank loan, to build the dam both to supplement the Indus's dry-season flows and to generate electricity. The dam is run by Pakistan's Water and Power Development Authority (WAPDA), the state body that owns and operates the country's largest hydropower plants. The 1992 report gives the dam's cost as over $2 billion in 1973.

The first filling of the reservoir went badly. According to the 1992 report, several of the dam's features were designed to carry discharges and flow speeds never before handled at any dam, and during the first reservoir filling in the summer of 1974 the power and irrigation tunnels, the stilling basins and spillway structures were damaged, and sinkholes were found in the dam's impervious blanket and upstream face. Repair work began at once and continued for years; the Tarbela Development Fund, which paid for it, was not closed until the end of December 1991. The World Bank's 2012 appraisal concluded that, despite those early failures, the dam has been extremely safe since then, and that its safety had improved as silt settling in the reservoir reduced seepage through the dam. The AIIB dates the completed dam to 1976.

Sedimentation

Tarbela's reservoir traps sediment carried down by the Indus. In 2012 the World Bank estimated that the reservoir had lost about 30 percent of its capacity in the 36 years since commissioning. Its figures show gross storage falling from 11.620 million acre-feet (about 14.3 billion cubic metres) when the dam was commissioned to 7.732 million acre-feet (about 9.5 billion cubic metres) by 2012, and live storage, the part that can actually be released, from 9.679 to 6.625 million acre-feet. An acre-foot is the volume of water that would cover one acre to a depth of one foot; the Bank's conversion is 1 million acre-feet to 1.234 billion cubic metres.

The silt has built up into a delta inside the reservoir that creeps toward the dam. In 2012 the Bank put its front about 14 km from the intake of the powerhouse. To keep sediment out of the turbines, the reservoir's dead storage level, below which water is not normally drawn off, was raised to 1,378 feet above sea level on 1 August 2010, and raised intakes were added to the power tunnels in the later extensions. The Bank considered the dam's useful life to be more than 80 years, and noted that dams planned upstream, such as Diamer-Basha, would trap sediment and so extend Tarbela's life. It also recorded the wider cost: storage lost to sedimentation at Tarbela and at the Mangla reservoir exceeds the roughly 2.9 million acre-feet added by raising Mangla Dam, and canal diversions for irrigation, which reached as high as 105 million acre-feet a year after Tarbela was built, averaged 94.5 MAF in 2001 to 2010.

Resettlement

The resettlement of people for the dam left problems that lasted for decades. The World Bank's 2012 document describes the poor implementation of the Tarbela resettlement program, dating back more than 30 years, as having left difficult outstanding issues. At that time 40 claims from the original Tarbela project and 410 from the later Ghazi Barotha hydropower project, which runs on water released from Tarbela, were still pending in Pakistan's courts, and the Bank's project financed a programme to settle them. The AIIB reported in 2016 that several of these legacy cases had been addressed through a Resettlement Commission and that the commission would continue its work.

Power extensions

Hydropower units were first installed on three of the dam's tunnels. By 2012 the dam had an installed capacity of 3,478 megawatts (MW). The Fourth Extension, approved by the World Bank on 20 March 2012, added a 1,410 MW powerhouse on Tunnel 4 and has been in operation since 2018; the World Bank reported in May 2026 that it had generated more than 32,548 gigawatt-hours (GWh) since commissioning. With it, the Bank gives the Tarbela complex 4,888 MW of dependable capacity and an annual output of 17,000 to 18,000 GWh, about half of WAPDA's hydropower output.

The Fifth Extension converts Tunnel 5, previously used only to release irrigation water, into a 1,530 megawatt (MW) powerhouse, which would bring the dam's capacity to 6,418 MW (4,888 plus 1,530). It is financed by a World Bank loan of $390 million approved on 20 September 2016, a $300 million loan from the AIIB approved a week later, and money from WAPDA. The World Bank's document of 7 May 2026 described a further $300 million to cover a cost overrun, which it attributed to inflation, larger quantities of work, the need to replace and rehabilitate the gates in Tunnel 5, and interest during construction. It expected the generating units to be commissioned in July 2027.

Cofferdam failures

A cofferdam is a temporary barrier built to keep water out of a construction site. Pakistani business news site Profit, citing the newspaper Dawn, reported on 13 July 2026 that a government inquiry into an August 2025 cofferdam collapse at the Fifth Extension site had held the contractor, the consultant and WAPDA responsible, finding that unauthorised design changes and contractual violations contributed to the failure. According to that report, the inquiry found that river flows at the time were within Tarbela's historical range and well below the cofferdam's design capacity. The report said the collapse delayed the project by at least two years, raised its estimated cost from Rs82.36 billion in 2017 to Rs317 billion, and moved its expected completion to the end of June 2028.

On 9 November 2026 Al Jazeera reported that a protective barrier collapsed at the partly built Fifth Extension project in Khyber Pakhtunkhwa province, causing a flood; a worker swept away was rescued and no casualties were reported. The report gave no cause.